Header DolWin3

Annual peak load and load curve

The load curve in the form of the grid feed-in is the sum total of all feed of grid transfer points, power plants, and distribution networks into the maximum voltage network (network area 1) in the control area of TenneT TSO GmbH.

Load curve

The load curve is the sum of the grid losses and all purchases (own consumption) of the connected converter platforms and wind farms in the grid of the offshore company

Provisional annual peak load

The annual peak load corresponds to the maximum value of the respective load curve in a calendar year. You can see the annual peak load by selecting "this year" in the date range picker. The minimum and maximum values are marked with an arrow in the curve chart.

No Data found in specified Daterange

Annual peak load

of the years 2018 - 2024

2024 Maximum voltage

30 MW on 23.02.2024 10:45am

2023 Maximum voltage

30 MW on 21.04.2023 6:15am

2022 Maximum voltage

27 MW on 05.04.2022 11:15pm  

2021 Maximum voltage

30 MW on 07.04.2021 11:45am  

2020 Maximum voltage

28 MW on 01.02.2020 9:15am  

2019 Maximum voltage

26 MW on 28.11.2019 21:00pm  

2018 Maximum voltage

20 MW on 11.09.2018 6:00am